Project Eagle


February 4, 2007
- Cardboard cabinet patterns, To-do list, Calculate tanks, Stain test, Eagle window, Bedroom wallpaper -

During the week I made a couple patterns for the bedroom cabinets.

Our heads were starting to spin with thoughts of everything that can be done now, and trying to figure out what needs to be done first. So we made a to-do list, and then chose a couple tasks from the list to get done this weekend.

  • Finish DS wall-liner. **
  • CS wall-liner in bdrm. **
  • Wallpaper bedroom. **
  • Bedroom cabinets.
  • Bdrm nightstands.
  • Raised floor in bdrm.
  • Bed frame cover.
  • Bdrm lights and outlets.
  • Rope lighting in bdrm.
  • Vinyl ceiling in bdrm.
  • Measure bays for tanks **
  • Order tanks
  • Call Artistcraft
  • Order shower

  • Body work bfr paint
  • Visor
  • Call paint shops 4 est

  • Pick wood & stain **

Note: ** indicates what we chose to get done this weekend

We bought one piece of hardwood, and cut it into 1 foot sections. I marked each piece of wood, and tried different combinations of stain, pre-stain conditioner and polyurethane to figure if this is the wood we want, and how to treat it.

Art measured the bay space, and calculated the tank dimentions.

I picked up the eagle window (take two) this past week, so here is the new one going in.

This is Art *trying* to tell me to quit messing with the camera and "Get to work" -- He's so cute - he makes me laugh a lot!!

Notice who is working (and who is still messing around with the camera) !!

The wall-liner and wallpaper is done in the bedroom. We're probably going to pick up some lumber next Friday ... woooo-hooo