Project Eagle


January 24, 2006
Leakproofing and framing

Now we are concentrating on the tasks that need to get done before we insulate the walls and ceiling. We've ordered the Handi-foam, spray on insulation, and our windows. It will take the windows about a month to get here, but the insulation was here in a week! Art welded frame inside the front cap, and the 14"x14" frames for roof airs. We also have done some leak patrol and patching.. however, there is one leak that we have yet to find the origin.