Take a look at the new siding!





The first side went up beautifully! You really can't ask for better friends. Everyone was here early, and worked as if they were working on their own buses! It took 8 hours and 448 rivets to complete this side. We want to try to combine the second side with our annual Labor Day campout on September 3rd, so stay tuned. Between now and then we'll be finishing up the aluminum siding on this side, and getting the other side ready.